Bond Information 


 GHS Construction Picture Updates


November 2007 Update 1
November 2007 Update 2

October 1 &2, 2007


September 20,  2007


September 7, 2007


Gainesville Independent School District Construction Update – New High School August 20, 2007

The steel framing is being erected as well as the joists in the cafeteria, kitchen, band, choir, drama, gymnasiums, science rooms, and regular classrooms.  Concrete foundation has been completed in all but four areas and the music, drama, cafeteria and kitchen will be poured this week.  That will leave the gym dressing rooms, field house, auto tech/agriculture buildings to be poured.

The roofing for the gymnasium will begin tomorrow.  Roof decking has been placed on one classroom area and is being continued on the other portions of the building.  Site grading in preparation for pouring the North drive, bus loop, parking in front of the building and front car loop is almost completed.  Plumbing and electrical work is also occurring on all portions of the building.


Gainesville High School Construction
Photo Update
July 23, 2007


Gainesville High School Construction
Photo Update
June 25, 2007


Gainesville Independent School District
 New High School Construction Update
MAY 30, 2007

Construction activities for the new high school have been moving along well until the rain has slowed things down lately.  The new high school is scheduled for completion in April 2008.  Presently, the southern drive has been completed with the exception of the approaches, site grading is about 95% complete, building pad preparation is 95% complete, the student parking lot has been mostly completed, storm sewer is 90% complete, on-site sanitary sewer is about 90% complete,  off-site water lines are 50% complete, underground plumbing is currently being placed in and around the building pad.  


Gainesville High School Design and Floor Plan

Click to enlarge

The Gainesville I.S.D Board of Trustees recently unanimously voted to approve the building type and site location for the new high school.  The new high school which will be located between the frontage road of Interstate 35 and 1306 will face Interstate 35, be constructed near the center of the district owned property, and will consist of approximately 180,000 square feet.  The new school is designed for future expansion of all academic and core areas should the need arise.  The campus will have students in grades nine through twelve and is originally being designed for 1,000 students in the academic areas with the building accommodating 1,200 students in the core areas.  The district architects and engineers are currently working on both off-site utility plans and building plans.  The construction of off-site utilities will occur first and will be followed by the school building construction. 

Student and bus access to the school will occur off of 1306.  Only staff and visitor parking will be in front of the school with student parking being located in back of the school.  There will also be staff parking on both the North and South sides of the school building.


Click to enlarge
Click to enlarge