Detailed Project Updates
Below are the updates provided by WRA Architects and BTC Construction at the October 20206 Bond Oversight meeting.
WRA Architects BTC Construction
As of October 2026, the current financial breakdown projections are as follows:
Phase 1 - Budgeted $33,854,222 / Actual $32,562,769 ($1,291,453 under)
Phase 2 - Budgeted $24,979,577 / Actual $26,197,030 ($1,217,453 over)
Overall - Bond amount #58,533,7699 / Actual $58,459,760 ($74,039 under)
Construction Drone Photos
Bond Project Scope & Timeline
Current Project: May 2025 - March 2026
- Gainesville Junior High: library expansion, entryway, secure vestibule, roof replacement, RTUs, parking lots, and sidewalks.
Phase 1: May 2026 through December 2027
- Edison Elementary: 8 classroom addition, secure vestibule, fire alarm, PA system, new gym/storm shelter, cafeteria expansion, library addition, new flooring
- Chalmers Elementary: 8 classroom addition/storm shelter, secure fencing, parking lot, playground
- Intermediate: 8 classroom addition, secure fencing, fire alarm, parking lot, playground
Schematic Designs:
Edison Chalmers Intermediate
Phase 2: November 2026 through July 2028
start time will be approximately 6 months after Phase 1 begins
Schematic Designs - Junior High and High School
Junior High: enclose F hall, secure fencing, fire alarm, cafeteria expansion
High School: PA, secure vestibule, door locks, new CTE wing and black box theater; CTE wing will include space for Culinary Arts, Visual Arts, Robotics, and Health Sciences