2025 Bond

Bond Project Scope & Timeline

Current Project: May 2025 - January 2026

  • Gainesville Junior High: library expansion, , secure vestibule, roof replacement, RTUs, parking lots, and sidewalks. 

Phase 1: May 2026 through December 2027 

  • Edison Elementary: 8 classroom addition, secure vestibule, fire alarm, PA system, new gym/storm shelter, cafeteria expansion, library addition, new flooring
  • Chalmers Elementary: 8 classroom addition/storm shelter, secure fencing, parking lot, playground
  • Intermediate: 8 classroom addition, secure fencing, fire alarm, parking lot, playground
  • Schematic Designs: 
    Edison Chalmers Intermediate 
  • Interior Renderings

Phase 2: November 2026 through July 2028 

start time will be approximately 6 months after Phase 1 begins

Junior High: secure vestibule, enclose F hall, secure fencing, fire alarm, new roof, RTUs, parking lot, sidewalks, cafeteria expansion, library expansion

High School: PA, secure vestibule, door locks, new CTE wing and black box theater; CTE wing will include space for Culinary Arts, Visual Arts, Robotics, and Health Sciences