Bond 2025 update Oct 2026

On October 20, the Bond Oversight Committee met and heard a detailed update from both WRA Architects and BTC Construction.  The Phase 1 projects at Edison, Chalmers, and Intermediate are well underway and the Phase 2 projects at GJH and GHS have kicked off. 

As of October 2026, the current financial projections are as follows:

Phase 1 - Budgeted $33,854,222 / Actual $32,562,769 ($1,291,453 under)

Phase 2 - Budgeted $24,979,577 / Actual $26,197,030 ($1,217,453 over)

Overall - Bond amount #58,533,7699 / Actual $58,459,760 ($74,039 under)

The full presentation from both entities, as well as drone photos of all construction sites, are available on the Bond 2025 webpage.